Storage Structure for Transit Action Buses

Red Deer, Alberta

completePublic TransitPTIF
Federal contribution
$1.1M
$1,091,202
Federal share49%

of $2.2M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedDec 3, 2016
20172018201920202021
Built

Approved 4 weeks before the announcement.

Program
Public Transit Infrastructure Fund
Ultimate recipient
City of Red Deer
Construction start
Jun 1, 2017(actual)
Construction end
Jun 30, 2021(actual)

Against the original forecast

  • Construction start2 months lateforecast Apr 1, 2017