Bus Stop Accessibility Upgrades
Federal contribution
$891,427
Federal share42%
of $2.1M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedDec 3, 2016
2017201920212023
Built
Approved 4 weeks before the announcement.
- Program
- Public Transit Infrastructure Fund
- Ultimate recipient
- City of Red Deer
- Construction start
- Jun 1, 2017(actual)
- Construction end
- Nov 30, 2022(actual)
Against the original forecast
- Construction start2 months lateforecast Apr 1, 2017
- Construction end10 months lateforecast Jan 30, 2022