Bus Stop Accessibility Upgrades

Red Deer, Alberta

completePublic TransitPTIF
Federal contribution
$891,427
Federal share42%

of $2.1M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedDec 3, 2016
2017201920212023
Built

Approved 4 weeks before the announcement.

Program
Public Transit Infrastructure Fund
Ultimate recipient
City of Red Deer
Construction start
Jun 1, 2017(actual)
Construction end
Nov 30, 2022(actual)

Against the original forecast

  • Construction start2 months lateforecast Apr 1, 2017
  • Construction end10 months lateforecast Jan 30, 2022