Oak Street West Sidewalk Extension

Leamington, Ontario

completePublic TransitPTIF
Federal contribution
$65,000
Federal share50%

of $130.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 31, 2017
2017
Built

Approved 3 months before the announcement.

Program
Public Transit Infrastructure Fund
Ultimate recipient
Municipality of Leamington
Construction start
Jan 1, 2017(actual)
Construction end
Dec 15, 2017(actual)

Against the original forecast

  • Construction start6 months earlyforecast Jul 1, 2017
  • Construction end6 weeks lateforecast Oct 31, 2017