Rehabilitation of Dundas Place
Federal contribution
$7.9M
$7,881,339
Federal share49%
of $16.0M total eligible cost; the rest comes from other partners.
Schedule
AnnouncedMar 31, 2017
ApprovedJul 10, 2017
2018201920202021
Built
Approved 3 months after the announcement.
- Program
- Public Transit Infrastructure Fund
- Ultimate recipient
- Corporation of the City of London
- Construction start
- Apr 1, 2018(actual)
- Construction end
- Jul 31, 2021(actual)
Against the original forecast
- Construction start2 years lateforecast Apr 1, 2016
Also in London
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 48144 in the federal list. How to read these figures.