New Accessible Transit Pads and Sidewalks
Federal contribution
$1.0M
$1,000,000
Federal share50%
of $2.0M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 31, 2017
20182019
Built
Approved 7 weeks before the announcement.
- Program
- Public Transit Infrastructure Fund
- Ultimate recipient
- Corporation of the City of London
- Construction start
- Aug 1, 2017(actual)
- Construction end
- Dec 31, 2018(actual)
Against the original forecast
- Construction start7 weeks lateforecast Jun 15, 2017
- Construction end4 months lateforecast Sep 1, 2018