Kiwanis Park Pathway Connection

London, Ontario

completeActive TransportationPTIF
Federal contribution
$1.0M
$1,048,917
Federal share50%

of $2.1M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 31, 2017
2018
Built

Approved 7 weeks before the announcement.

Program
Public Transit Infrastructure Fund
Construction start
Jun 15, 2017(actual)
Construction end
Nov 30, 2018(actual)

Against the original forecast

  • Construction end2 months lateforecast Sep 30, 2018