Construct New Downtown Cycle Tracks
Federal contribution
$875,000
Federal share50%
of $1.8M total eligible cost; the rest comes from other partners.
Schedule
AnnouncedMar 31, 2017
ApprovedJul 10, 2017
20182019
Built
Approved 3 months after the announcement.
- Program
- Public Transit Infrastructure Fund
- Ultimate recipient
- Corporation of the City of London
- Construction start
- Sep 1, 2017(actual)
- Construction end
- Jun 30, 2019(actual)
Against the original forecast
- Construction start3 months lateforecast Jun 1, 2017
- Construction end11 months lateforecast Jul 31, 2018
Also in London
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 48150 in the federal list. How to read these figures.