Byron Baseline and Wonderland Road Sidewalk and Bicycle Facilities
Federal contribution
$811,056
Federal share46%
of $1.8M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 31, 2017
20182019
Built
Approved 7 weeks before the announcement.
- Program
- Public Transit Infrastructure Fund
- Ultimate recipient
- Corporation of the City of London
- Construction start
- May 1, 2017(actual)
- Construction end
- Jun 30, 2019(actual)
Against the original forecast
- Construction end8 months lateforecast Oct 28, 2018
Also in London
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 48151 in the federal list. How to read these figures.