Construct Bradley Avenue Extension Transit and Active Transportation Features
Federal contribution
$224,167
Federal share45%
of $500.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 31, 2017
Built
Approved 7 weeks before the announcement.
- Program
- Public Transit Infrastructure Fund
- Ultimate recipient
- Corporation of the City of London
- Construction start
- Apr 15, 2017(actual)
- Construction end
- Dec 1, 2017(actual)
Against the original forecast
- Construction start4 weeks earlyforecast May 15, 2017
- Construction end2 months earlyforecast Jan 30, 2018
Also in London
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 48153 in the federal list. How to read these figures.