Construct Bradley Avenue Extension Transit and Active Transportation Features

London, Ontario

completeActive TransportationPTIF
Federal contribution
$224,167
Federal share45%

of $500.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 31, 2017
Built

Approved 7 weeks before the announcement.

Program
Public Transit Infrastructure Fund
Construction start
Apr 15, 2017(actual)
Construction end
Dec 1, 2017(actual)

Against the original forecast

  • Construction start4 weeks earlyforecast May 15, 2017
  • Construction end2 months earlyforecast Jan 30, 2018

Also in London

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 48153 in the federal list. How to read these figures.