Sidewalk and Bicycle Lane Improvements on the Field Marshall Wolseley Bridge
Federal contribution
$74,241
Federal share39%
of $190.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 31, 2017
Built
Approved 7 weeks before the announcement.
- Program
- Public Transit Infrastructure Fund
- Ultimate recipient
- Corporation of the City of London
- Construction start
- Jul 1, 2017(actual)
- Construction end
- Aug 15, 2017(actual)
Against the original forecast
- Construction start7 weeks lateforecast May 15, 2017
- Construction end2 months earlyforecast Oct 30, 2017
Also in London
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 48154 in the federal list. How to read these figures.