Sidewalk and Bicycle Lane Improvements on the Field Marshall Wolseley Bridge

London, Ontario

completeActive TransportationPTIF
Federal contribution
$74,241
Federal share39%

of $190.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 31, 2017
Built

Approved 7 weeks before the announcement.

Program
Public Transit Infrastructure Fund
Construction start
Jul 1, 2017(actual)
Construction end
Aug 15, 2017(actual)

Against the original forecast

  • Construction start7 weeks lateforecast May 15, 2017
  • Construction end2 months earlyforecast Oct 30, 2017

Also in London

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 48154 in the federal list. How to read these figures.