Old East Village Shift Rapid Transit Route Parking Lot Improvements

London, Ontario

completePublic TransitPTIF
Federal contribution
$639,966
Federal share49%

of $1.3M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 31, 2017
20182019
Built

Approved 7 weeks before the announcement.

Program
Public Transit Infrastructure Fund
Construction start
Aug 1, 2017(actual)
Construction end
Dec 31, 2018(actual)

Against the original forecast

  • Construction start2 months lateforecast Jun 1, 2017
  • Construction end4 weeks lateforecast Nov 30, 2018

Also in London

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 48156 in the federal list. How to read these figures.