Old East Village Shift Rapid Transit Route Parking Lot Improvements
Federal contribution
$639,966
Federal share49%
of $1.3M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 31, 2017
20182019
Built
Approved 7 weeks before the announcement.
- Program
- Public Transit Infrastructure Fund
- Ultimate recipient
- Corporation of the City of London
- Construction start
- Aug 1, 2017(actual)
- Construction end
- Dec 31, 2018(actual)
Against the original forecast
- Construction start2 months lateforecast Jun 1, 2017
- Construction end4 weeks lateforecast Nov 30, 2018
Also in London
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 48156 in the federal list. How to read these figures.