Upgrade of on-board bus audio/video recording system
Federal contribution
$145,802
Federal share42%
of $350.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 31, 2017
2017201820192020
Built
Approved 7 weeks before the announcement.
- Program
- Public Transit Infrastructure Fund
- Ultimate recipient
- Corporation of the City of London
- Construction start
- Sep 1, 2017(actual)
- Construction end
- Feb 28, 2020(actual)
Against the original forecast
- Construction start4 months lateforecast May 1, 2017
- Construction end5 weeks earlyforecast Mar 31, 2020
Also in London
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 48162 in the federal list. How to read these figures.