Modernization of Greenwood Subdivision Wastewater Treatment Facility
Federal contribution
$708,172
Federal share47%
of $1.5M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJan 20, 2017
201720182019
Built
Approved 5 weeks before the announcement.
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- City of Saint John
- Construction start
- Jul 9, 2018(actual)
- Construction end
- Jun 28, 2019(actual)
Against the original forecast
- Construction start3 months lateforecast Apr 21, 2018
- Construction end9 months earlyforecast Mar 31, 2020
Also in Saint John
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 48196 in the federal list. How to read these figures.