Back to projects

Modernization of Greenwood Subdivision Wastewater Treatment Facility

Saint John, New Brunswick

completeWastewaterCWWF
Federal contribution
$708,172
Federal share47%

of $1.5M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJan 20, 2017
201720182019
Built

Approved 5 weeks before the announcement.

Program
Clean Water and Wastewater Fund
Ultimate recipient
City of Saint John
Construction start
Jul 9, 2018(actual)
Construction end
Jun 28, 2019(actual)

Against the original forecast

  • Construction start3 months lateforecast Apr 21, 2018
  • Construction end9 months earlyforecast Mar 31, 2020

Also in Saint John

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 48196 in the federal list. How to read these figures.