Combined/Sanitary Sewer System - CSO/SSO Controls Installation

Saint John, New Brunswick

completeWastewaterCWWF
Federal contribution
$408,073
Federal share50%

of $816.1K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJan 20, 2017
201720182019
Built

Approved 5 weeks before the announcement.

Program
Clean Water and Wastewater Fund
Ultimate recipient
City of Saint John
Construction start
Oct 7, 2017(actual)
Construction end
Oct 11, 2019(actual)

Against the original forecast

  • Construction start6 weeks lateforecast Aug 28, 2017
  • Construction end2 months lateforecast Jul 31, 2019