Schedule

Announced and approvedJan 20, 2017
201720182019
Built

Approved 5 weeks before the announcement.

Program
Clean Water and Wastewater Fund
Ultimate recipient
City of Saint John
Construction start
Jun 27, 2018(actual)
Construction end
Jun 28, 2019(actual)

Against the original forecast

  • Construction start2 months lateforecast Apr 21, 2018
  • Construction end9 months earlyforecast Mar 31, 2020