Back to projects

Tilley Avenue - Sewer Separation

Saint John, New Brunswick

completeWastewaterCWWF
Federal contribution
$226,707
Federal share50%

of $453.4K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJan 20, 2017
20172018
Built

Approved 5 weeks before the announcement.

Program
Clean Water and Wastewater Fund
Ultimate recipient
City of Saint John
Construction start
Sep 11, 2017(actual)
Construction end
Jan 24, 2018(actual)

Against the original forecast

  • Construction start7 weeks lateforecast Jul 24, 2017
  • Construction end5 months earlyforecast Jun 29, 2018

Also in Saint John

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 48200 in the federal list. How to read these figures.