Tilley Avenue - Sewer Separation
Federal contribution
$226,707
Federal share50%
of $453.4K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJan 20, 2017
20172018
Built
Approved 5 weeks before the announcement.
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- City of Saint John
- Construction start
- Sep 11, 2017(actual)
- Construction end
- Jan 24, 2018(actual)
Against the original forecast
- Construction start7 weeks lateforecast Jul 24, 2017
- Construction end5 months earlyforecast Jun 29, 2018
Also in Saint John