District Metering Program
Federal contribution
$351,646
Federal share48%
of $725.5K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJan 20, 2017
20172018
Built
Approved 5 weeks before the announcement.
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- City of Saint John
- Construction start
- Oct 16, 2017(actual)
- Construction end
- Apr 5, 2018(actual)
Against the original forecast
- Construction start7 weeks lateforecast Aug 28, 2017
- Construction end23 months earlyforecast Feb 28, 2020
Also in Saint John
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 48203 in the federal list. How to read these figures.