Sanitary Sewer - LeBreton Street
Federal contribution
$100,000
Federal share50%
of $200.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJan 20, 2017
2017
Built
Approved 5 weeks before the announcement.
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Village of Neguac
- Construction start
- May 23, 2017(actual)
- Construction end
- Dec 5, 2017(actual)
Against the original forecast
- Construction start2 weeks earlyforecast Jun 8, 2017
- Construction end4 months lateforecast Jul 31, 2017