New Artesian Well and Associated Work

St. George's, Newfoundland and Labrador

completeDrinking WaterSCF
Federal contribution
$17,431
Federal share17%

of $105.2K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 3, 2017
Built

Approved 4 weeks before the announcement.

Program
Provincial-Territorial Infrastructure Component - Small Communities Fund
Construction start
Aug 7, 2017(actual)
Construction end
Oct 17, 2017(actual)

Against the original forecast

  • Construction start5 months lateforecast Mar 1, 2017
  • Construction end2.3 years earlyforecast Feb 21, 2020

Also in St. George's

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 48277 in the federal list. How to read these figures.