Replacement of bus wash infrastructure at Highbury Transit Facility

London, Ontario

completePublic TransitPTIF
Federal contribution
$367,461
Federal share50%

of $736.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 31, 2017
2018
Built

Approved 7 weeks before the announcement.

Program
Public Transit Infrastructure Fund
Construction start
Aug 1, 2017(actual)
Construction end
Mar 31, 2018(actual)

Against the original forecast

  • Construction start3 months lateforecast May 1, 2017