Replacement of bus wash infrastructure at Highbury Transit Facility
Federal contribution
$367,461
Federal share50%
of $736.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 31, 2017
2018
Built
Approved 7 weeks before the announcement.
- Program
- Public Transit Infrastructure Fund
- Ultimate recipient
- Corporation of the City of London
- Construction start
- Aug 1, 2017(actual)
- Construction end
- Mar 31, 2018(actual)
Against the original forecast
- Construction start3 months lateforecast May 1, 2017
Also in London
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 48284 in the federal list. How to read these figures.