Replacement Dual Power Invertor Modules for 8 Hybrid buses

London, Ontario

completePublic TransitPTIF
Federal contribution
$200,000
Federal share50%

of $400.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 31, 2017
2018
Built

Approved 7 weeks before the announcement.

Program
Public Transit Infrastructure Fund
Construction start
Sep 1, 2017(actual)
Construction end
Mar 31, 2018(actual)

Against the original forecast

  • Construction start4 months lateforecast May 1, 2017