Replace security gate infrastructure at Highbury Transit Facility

London, Ontario

completePublic TransitPTIF
Federal contribution
$72,486
Federal share48%

of $150.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 31, 2017
20182019
Built

Approved 7 weeks before the announcement.

Program
Public Transit Infrastructure Fund
Construction start
Jul 1, 2017(actual)
Construction end
Dec 31, 2018(actual)

Against the original forecast

  • Construction start2 months lateforecast May 1, 2017

Also in London