Completion of concrete repair at Wonderland Transit Facility

London, Ontario

completePublic TransitPTIF
Federal contribution
$74,590
Federal share50%

of $150.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 31, 2017
2018
Built

Approved 7 weeks before the announcement.

Program
Public Transit Infrastructure Fund
Construction start
Nov 1, 2017(actual)
Construction end
Jun 30, 2018(actual)

Against the original forecast

  • Construction start6 months lateforecast May 1, 2017
  • Construction end3 months lateforecast Mar 31, 2018

Also in London

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 48295 in the federal list. How to read these figures.