Purchase and installation of 72 Automatic Passenger Counters for remainder of bus fleet

London, Ontario

completePublic TransitPTIF
Federal contribution
$217,650
Federal share38%

of $575.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 31, 2017
2017201820192020
Built

Approved 7 weeks before the announcement.

Program
Public Transit Infrastructure Fund
Construction start
Jul 1, 2017(actual)
Construction end
Mar 28, 2020(actual)

Against the original forecast

  • Construction start2 months lateforecast May 1, 2017
  • Construction end3 months lateforecast Dec 31, 2019

Also in London

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 48300 in the federal list. How to read these figures.