Increased bus replacement program in 2017 to include 7 buses planned for 2018 replacement
Federal contribution
$2.0M
$1,981,373
Federal share50%
of $4.0M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 31, 2017
2017
Built
Approved 7 weeks before the announcement.
- Program
- Public Transit Infrastructure Fund
- Ultimate recipient
- Corporation of the City of London
- Construction start
- Jan 1, 2017(actual)
- Construction end
- Oct 31, 2017(actual)
Against the original forecast
- Construction end2 months earlyforecast Dec 31, 2017
Also in London
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 48302 in the federal list. How to read these figures.