12 Audible Pedestrian Signal Upgrades
Federal contribution
$195,000
Federal share50%
of $390.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 31, 2017
2018
Built
Approved 7 weeks before the announcement.
- Program
- Public Transit Infrastructure Fund
- Ultimate recipient
- Corporation of the City of London
- Construction start
- Nov 1, 2017(actual)
- Construction end
- Jun 29, 2018(actual)
Against the original forecast
- Construction start4 months lateforecast Jul 3, 2017
- Construction end5 weeks earlyforecast Jul 31, 2018
Also in London
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 48307 in the federal list. How to read these figures.