Installation of 60 Pedestrian Countdown Signal Heads
Federal contribution
$100,000
Federal share50%
of $200.0K total eligible cost; the rest comes from other partners.
Schedule
AnnouncedMar 31, 2017
ApprovedJul 10, 2017
Built
Approved 3 months after the announcement.
- Program
- Public Transit Infrastructure Fund
- Ultimate recipient
- Corporation of the City of London
- Construction start
- Jun 1, 2017(actual)
- Construction end
- Sep 30, 2017(actual)
Against the original forecast
- Construction start5 weeks earlyforecast Jul 3, 2017
- Construction end4 weeks earlyforecast Oct 30, 2017
Also in London