Bicycle Detection Improvements at 4 intersections
Federal contribution
$50,000
Federal share50%
of $100.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 31, 2017
Built
Approved 7 weeks before the announcement.
- Program
- Public Transit Infrastructure Fund
- Ultimate recipient
- Corporation of the City of London
- Construction start
- Mar 1, 2017(actual)
- Construction end
- Oct 31, 2017(actual)
Against the original forecast
- Construction start4 months earlyforecast Jul 3, 2017
Also in London
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 48309 in the federal list. How to read these figures.