Back to projects

Oakdale Avenue watermain replacement from Westchester Crescent to Lincoln Avenue in conjunction with road and sidewalk improvements from Weschester Crescent to Disher Street

St. Catharines, Ontario

completeDrinking WaterCWWF
Federal contribution
$450,000
Federal share50%

of $900.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMay 24, 2017
201620172018
Built

Approved 3 weeks before the announcement.

Program
Clean Water and Wastewater Fund
Construction start
Jan 12, 2016(actual)
Construction end
Jun 30, 2018(actual)

Against the original forecast

  • Construction start15 months earlyforecast Apr 3, 2017
  • Construction end9 months lateforecast Sep 29, 2017

Also in St. Catharines