Back to projects

Brighton Street Sanitary Sewer Replacement from Garnet Street to Facer Street

St. Catharines, Ontario

completeWastewaterCWWF
Federal contribution
$135,000
Federal share50%

of $270.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMay 24, 2017
2018
Built

Approved 3 weeks before the announcement.

Program
Clean Water and Wastewater Fund
Construction start
Apr 24, 2017(actual)
Construction end
Jun 30, 2018(actual)

Against the original forecast

  • Construction end3 months lateforecast Mar 31, 2018

Also in St. Catharines