Brighton Street new storm sewer from Garnet Street to Facer Street

St. Catharines, Ontario

completeWastewaterCWWF
Federal contribution
$100,000
Federal share50%

of $200.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMay 24, 2017
20182019
Built

Approved 3 weeks before the announcement.

Program
Clean Water and Wastewater Fund
Construction start
Feb 1, 2017(actual)
Construction end
Dec 31, 2018(actual)

Against the original forecast

  • Construction start3 months earlyforecast Apr 24, 2017
  • Construction end9 months lateforecast Mar 31, 2018

Also in St. Catharines

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 48381 in the federal list. How to read these figures.