Upgrade/rehabilitation of storm sewers on Mill Street, village of St-Eugene that serves 12 residential houses and one (1) business.

East Hawkesbury, Ontario

completeWastewaterCWWF
Federal contribution
$50,000
Federal share44%

of $113.8K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMay 23, 2017
2018
Built

Approved 3 weeks before the announcement.

Program
Clean Water and Wastewater Fund
Construction start
May 15, 2017(actual)
Construction end
Jul 31, 2018(actual)

Against the original forecast

  • Construction end2 months lateforecast May 31, 2018

Also in East Hawkesbury

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 48441 in the federal list. How to read these figures.