Storm Sewer installation along Gustavus Street from Kaake Street to Bruce Street to eliminate failing infiltration galleries and watermain upgrade to meet growth demand

Saugeen Shores, Ontario

completeWastewaterCWWF
Federal contribution
$106,142
Federal share50%

of $212.3K total eligible cost; the rest comes from other partners.

Schedule

AnnouncedJun 16, 2017
ApprovedMar 27, 2018
2018
Built

Approved 9 months after the announcement.

Program
Clean Water and Wastewater Fund
Ultimate recipient
Town of Saugeen Shores
Construction start
Nov 9, 2017(actual)
Construction end
Jun 20, 2018(actual)

Against the original forecast

  • Construction start7 months lateforecast Apr 1, 2017
  • Construction end6 weeks earlyforecast Aug 1, 2018