Storm Sewer installation along Gustavus Street from Kaake Street to Bruce Street to eliminate failing infiltration galleries and watermain upgrade to meet growth demand
Federal contribution
$106,142
Federal share50%
of $212.3K total eligible cost; the rest comes from other partners.
Schedule
AnnouncedJun 16, 2017
ApprovedMar 27, 2018
2018
Built
Approved 9 months after the announcement.
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Town of Saugeen Shores
- Construction start
- Nov 9, 2017(actual)
- Construction end
- Jun 20, 2018(actual)
Against the original forecast
- Construction start7 months lateforecast Apr 1, 2017
- Construction end6 weeks earlyforecast Aug 1, 2018
Also in Saugeen Shores
- McEwing Bridge Replacement$1.1M
- Bruce County Road 17$434.8K
- Port Elgin - Storm Sewer outlet installation$338.4K
- Storm Sewer installation to eliminate failing infiltration galleries and watermain upgrade to meet growth demand (Outlet ca. 40 blocks in Port Elgin.)$272.8K
- Installation of New Watermain on Concession 6 to Facilitate Expansion for growth demand$221.0K
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 48446 in the federal list. How to read these figures.