Structural relining of 300mm watermain at the Flora Street river crossing.
Federal contribution
$100,000
Federal share50%
of $200.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMay 23, 2017
2018
Built
Approved 3 weeks before the announcement.
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- The Corporation of the Town of Carleton Place.
- Construction start
- May 1, 2017(actual)
- Construction end
- Jan 31, 2018(actual)
Against the original forecast
- Construction start3 months earlyforecast Aug 1, 2017
- Construction end4 weeks earlyforecast Feb 28, 2018
Also in Carleton Place
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 48495 in the federal list. How to read these figures.