Construction of new well at Municipal Office location to provide clean drinking water to the public
Federal contribution
$10,000
Federal share50%
of $20.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMay 23, 2017
Built
Approved 3 weeks before the announcement.
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Township of Hamilton
- Construction start
- Sep 15, 2017(actual)
- Construction end
- Nov 30, 2017(actual)
Against the original forecast
- Construction start6 weeks lateforecast Aug 1, 2017