Highlift Pump Rehabilitation at the Sheguiandah Water Treatment Plant
Northeastern Manitoulin and The Islands, Ontario
Federal contribution
$10,498
Federal share30%
of $35.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMay 24, 2017
2017
Built
Approved 3 weeks before the announcement.
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Town of Northeastern Manitoulin and the Islands
- Construction start
- Sep 12, 2016(actual)
- Construction end
- Mar 10, 2017(actual)
Against the original forecast
- Construction start6 months earlyforecast Mar 1, 2017
- Construction end9 months earlyforecast Nov 30, 2017
Also in Northeastern Manitoulin and The Islands
- Green Bush Road Rehabilitation$290.4K
- Upgrade Membrane Cassettes at Little Current Water Plant$166.6K
- NEMI Recreation Center Air Conditioner Upgrade$80.0K
- Indian Mountain Road Upgrade$74.6K
- Relocation and Replacement of Membrane Programmable Logic Controller (PLC) at the Little Current Water Treatment Plant$50.0K
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 48526 in the federal list. How to read these figures.