Back to projects

Interconnectivity valve replacement between clear wells

Opasatika, Ontario

completeDrinking WaterCWWF
Federal contribution
$5,000
Federal share50%

of $10.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMay 24, 2017
2018
Built

Approved 3 weeks before the announcement.

Program
Clean Water and Wastewater Fund
Ultimate recipient
Township of Opasatika
Construction start
Sep 10, 2018(actual)
Construction end
Dec 1, 2018(actual)

Against the original forecast

  • Construction start19 months lateforecast Feb 1, 2017
  • Construction end4 weeks lateforecast Oct 31, 2018