Interconnectivity valve replacement between clear wells
Federal contribution
$5,000
Federal share50%
of $10.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMay 24, 2017
2018
Built
Approved 3 weeks before the announcement.
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Township of Opasatika
- Construction start
- Sep 10, 2018(actual)
- Construction end
- Dec 1, 2018(actual)
Against the original forecast
- Construction start19 months lateforecast Feb 1, 2017
- Construction end4 weeks lateforecast Oct 31, 2018
Also in Opasatika
- Upgrade Supervisory Control and Data Acquisition (SCADA) & Programmable Logic Controller (PLC) at Water Treatment Plant$80.0K
- Opasatika Community Hub Renovation$52.9K
- Repair 7 hydrants in township to improve water distribution system effectiveness$14.0K
- Optimize green sand filter and diffusers$10.0K
- Repair main sewage pump house building$8.9K
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 48527 in the federal list. How to read these figures.