Construction of Kenny Drain-Industrial Park Storm Water Management Pond and Diversion Channel
Federal contribution
$880,000
Federal share50%
of $1.8M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJun 16, 2017
2018
Built
Approved 5 weeks before the announcement.
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Corporation of the City of Owen Sound
- Construction start
- Jul 24, 2017(actual)
- Construction end
- Aug 31, 2018(actual)
Against the original forecast
- Construction start3 months lateforecast May 1, 2017
- Construction end4 weeks earlyforecast Sep 30, 2018
Also in Owen Sound
- Owen Sound Secondary Sewage Upgrade$15.0M
- Construction of Owen Sound Multi-Purpose Recreation Facility$10.9M
- Reconstruction of the Grey-Bruce Line Road$4.1M
- Marine Emergency Duties Training and Research Centre at the Georgian College Owen Sound Campus$1.7M
- Owen Sound Water Treatment Plant Filtration System Improvements$1.6M
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 48532 in the federal list. How to read these figures.