Water and Wastewater Master Plan Study
Federal contribution
$6,914
Federal share12%
of $60.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMay 26, 2017
2018
Built
Approved 3 weeks before the announcement.
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Township of East Perth
- Construction start
- Jul 17, 2017(actual)
- Construction end
- Mar 15, 2018(actual)
Against the original forecast
- Construction start7 weeks lateforecast Jun 1, 2017
- Construction end2 weeks lateforecast Feb 28, 2018
Also in Perth East