Back to projects

Water and Wastewater Master Plan Study

Perth East, Ontario

completeDrinking WaterCWWF
Federal contribution
$6,914
Federal share12%

of $60.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMay 26, 2017
2018
Built

Approved 3 weeks before the announcement.

Program
Clean Water and Wastewater Fund
Ultimate recipient
Township of East Perth
Construction start
Jul 17, 2017(actual)
Construction end
Mar 15, 2018(actual)

Against the original forecast

  • Construction start7 weeks lateforecast Jun 1, 2017
  • Construction end2 weeks lateforecast Feb 28, 2018

Also in Perth East

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 48565 in the federal list. How to read these figures.