Rodney Sewage System Rehabilitation
Federal contribution
$293,427
Federal share50%
of $590.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJun 12, 2017
20182019
Built
Approved 5 weeks before the announcement.
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Municipality of West Elgin
- Construction start
- Sep 22, 2017(actual)
- Construction end
- Dec 31, 2018(actual)
Against the original forecast
- Construction start6 months lateforecast Apr 1, 2017
- Construction end9 months lateforecast Mar 31, 2018
Also in West Elgin
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 48619 in the federal list. How to read these figures.