Back to projects

Sediment Removal from Pond 52 to Restore Design Permanent Pool Volume of 560 m3

Waterloo, Ontario

completeWastewaterCWWF
Federal contribution
$109,027
Federal share50%

of $218.1K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 25, 2017
2018
Built

Approved 3 weeks before the announcement.

Program
Clean Water and Wastewater Fund
Ultimate recipient
City of Waterloo
Construction start
Nov 9, 2017(actual)
Construction end
Jun 4, 2018(actual)

Against the original forecast

  • Construction start9 months lateforecast Feb 1, 2017
  • Construction end10 months earlyforecast Mar 31, 2019

Also in Waterloo

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 48625 in the federal list. How to read these figures.