Sediment Removal from Pond 7 to Restore Design Permanent Pool Volume

Waterloo, Ontario

completeWastewaterCWWF
Federal contribution
$93,051
Federal share23%

of $396.5K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 25, 2017
201820192020
Built

Approved 3 weeks before the announcement.

Program
Clean Water and Wastewater Fund
Ultimate recipient
City of Waterloo
Construction start
Jan 10, 2018(actual)
Construction end
Dec 31, 2019(actual)

Against the original forecast

  • Construction start11 months lateforecast Feb 1, 2017

Also in Waterloo

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 48628 in the federal list. How to read these figures.