Electrical upgrades at the South Chatham-Kent Water Treatment Plant

Chatham-Kent, Ontario

completeDrinking WaterCWWF
Federal contribution
$144,000
Federal share50%

of $288.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJun 12, 2017
2017201820192020
Built

Approved 5 weeks before the announcement.

Program
Clean Water and Wastewater Fund
Construction start
Jun 1, 2016(actual)
Construction end
Mar 31, 2020(actual)

Against the original forecast

  • Construction end8 weeks lateforecast Feb 1, 2020

Also in Chatham-Kent

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 48662 in the federal list. How to read these figures.