Back to projects

Replacement of Archimedes Screw pumps at the Wallaceburg Water Pollution Control Plant

Chatham-Kent, Ontario

completeWastewaterCWWF
Federal contribution
$250,000
Federal share50%

of $500.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJun 12, 2017
201720182019
Built

Approved 5 weeks before the announcement.

Program
Clean Water and Wastewater Fund
Construction start
Nov 1, 2016(actual)
Construction end
Aug 1, 2019(actual)

Also in Chatham-Kent

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 48663 in the federal list. How to read these figures.