Woodward Wastewater Treatment Plant Methane Storage Facility refurbishment and exterior repainting.
Federal contribution
$1.6M
$1,568,138
Federal share39%
of $4.0M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJun 23, 2017
201820192020
Built
Approved 6 weeks before the announcement.
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- City of Hamilton
- Construction start
- Mar 6, 2017(actual)
- Construction end
- Mar 31, 2020(actual)
Against the original forecast
- Construction start4 months earlyforecast Jul 5, 2017
- Construction end2 years lateforecast Mar 31, 2018
Also in Hamilton
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 48691 in the federal list. How to read these figures.