Construction of new Lynden Water Treatment System
Federal contribution
$1.3M
$1,300,000
Federal share50%
of $2.6M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJun 23, 2017
201820192020
Built
Approved 6 weeks before the announcement.
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- City of Hamilton
- Construction start
- Jun 14, 2017(actual)
- Construction end
- Sep 30, 2020(actual)
Against the original forecast
- Construction start3 months earlyforecast Sep 1, 2017
- Construction end4 weeks earlyforecast Oct 31, 2020
Also in Hamilton
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 48693 in the federal list. How to read these figures.