Freelton Water Tower Structural Upgrades

Hamilton, Ontario

completeDrinking WaterCWWF
Federal contribution
$712,500
Federal share50%

of $1.4M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJun 23, 2017
201820192020
Built

Approved 6 weeks before the announcement.

Program
Clean Water and Wastewater Fund
Ultimate recipient
City of Hamilton
Construction start
May 19, 2017(actual)
Construction end
Mar 31, 2020(actual)

Against the original forecast

  • Construction end3 weeks lateforecast Mar 9, 2020