Western Interceptor Sewer CCTV and Sonar Inspection
Federal contribution
$335,152
Federal share24%
of $1.4M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJun 23, 2017
201820192020
Built
Approved 6 weeks before the announcement.
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- City of Hamilton
- Construction start
- Aug 1, 2017(actual)
- Construction end
- Mar 31, 2020(actual)
Against the original forecast
- Construction start7 months lateforecast Jan 2, 2017
- Construction end6 months lateforecast Sep 30, 2019
Also in Hamilton
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 48697 in the federal list. How to read these figures.