Design and Construction of Stormwater Quality Control Improvement at Existing Storm Sewer Outfall
Federal contribution
$325,000
Federal share50%
of $650.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMay 23, 2017
201820192020
Built
Approved 2 weeks before the announcement.
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Town of Ajax
- Construction start
- Aug 1, 2017(actual)
- Construction end
- Nov 30, 2019(actual)
Against the original forecast
- Construction start5 months lateforecast Feb 21, 2017
- Construction end2 months lateforecast Sep 27, 2019