Back to projects

Upgrade very large culvert Devil's Door Rd.

Front of Yonge, Ontario

completeWastewaterCWWF
Federal contribution
$9,500
Federal share50%

of $19.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMay 23, 2017
Built

Approved 2 weeks before the announcement.

Program
Clean Water and Wastewater Fund
Ultimate recipient
Township of Front of Yonge
Construction start
Aug 28, 2017(actual)
Construction end
Aug 30, 2017(actual)

Against the original forecast

  • Construction start4 months lateforecast May 1, 2017
  • Construction end2 months earlyforecast Oct 31, 2017